OK, Just got off the phone with Bill. You can tell he is stressed out first of all. Let me remind everyone that he is not "Edelbrock". He is a single guy bringing us a quality Head...just takes a while.
He said that the Caps are done at the Machine Shop. Heads will be worked on in about 2 weeks. He said that if there are no problems (and thats a big if!) we are looking at 3 to 3.5 weeks to get the heads from the Machine shop.
He also stated that he cannot go pick them up piece meal. When they are all done being machined, he picks them up to put on the finishing touches (Seats, remove burs,etc. basically making them perfect.)
Hope this info was of some assistance to you all.
|