I haven't had a chance to do much to the shed lately, so it was nice to get the formwork in place for the slab. Because there won't be a swarm of people here when the concrete is poured, and because only one person knows what they're doing, we are taking the careful option and doing the slab in two pours. For the slab size, I was glad to hear the concrete rep agree with our idea. He said he actually preferred to do two pours. It certainly reduces the risk of the concrete getting away from us, so that's the plan.
Spent some time checking and double checking levels, so hopefully we will end up with something that appears semi professional at a glance...
For no other reason than sparks look cool.
...and then the rain came down again...!
It is pouring down as I type this, so I'm fully expecting the moisture barrier to have become a pool by the morning. Fun times...